QLD · Safeguard Mechanism 2024–25

Burton Complex

BOWEN COKING COAL LIMITED
📍 QLD

The Safeguard Mechanism requires Australia's largest industrial facilities to keep net emissions under a legislated, stepping-down baseline — or offset the difference with carbon credits.

Burton Complex came in under its baseline in 2024–25 — reporting 174 kt against an obligation of 183 kt.
Source: Clean Energy Regulator · data as at 25 Oct 2026
174 kt
2024–25 emissions CER
183 kt
net baseline obligation CER
-9 kt
vs baseline Zerra calc.
—
ACCUs surrendered CER

Reported emissions vs baseline, 2023–24 to 2024–25

Red bars indicate emissions above baseline — covered by carbon credit purchases
0t51kt102kt154kt205kt23–2424–25 Emissions Overage Baseline

Credit surrenders — Burton Complex

YearEmissionsBaseline Gap†ACCUsSMCsCompliance†
24–25 174 kt 183 kt -9 kt — — Under baseline
23–24 168 kt 165 kt +3 kt 2,612 — ACCU buyer

Emissions, baseline, ACCUs and SMCs are reported directly by CER. †Gap and compliance category are calculated by Zerra from those figures.

What this means

Burton Complex is a facility operated by BOWEN COKING COAL LIMITED in QLD. Like all covered facilities, industrial operations generate significant emissions. Under Australia's Safeguard Mechanism, Burton Complex must keep its annual emissions below a stepping-down baseline — or purchase carbon credits to cover any overage.

In 2024–25, Burton Complex came in under its baseline — reporting emissions of 174 kt against an obligation of 183 kt, a surplus of 9 kt. Facilities that come in under baseline can generate Safeguard Mechanism Credits (SMCs), which can be sold to facilities that need to cover an overage.

Among 8 comparable facilities, 8 reported emissions above their baseline in 2024–25. The table below compares Burton Complex with other facilities covered by the Safeguard Mechanism in the same classification.

Related facilities — Safeguard Mechanism 2024–25

Facility Operator State Emissions vs Baseline Compliance
Moranbah North Mine ANGLO COAL (MORANBAH NORTH MANAGEMENT) PTY LIMITED QLD 1.41 Mt +761 kt ACCU + SMC
Curragh Mine CORONADO AUSTRALIA HOLDINGS PTY LTD QLD 1.09 Mt +558 kt Pending
Kestrel Mine Kestrel Coal Group Pty Ltd QLD 1.26 Mt +555 kt ACCU + SMC
Ashton Coal Mine (Underground) ASHTON COAL OPERATIONS PTY LIMITED NSW 683 kt +489 kt ACCU buyer
Goonyella Broadmeadow Mine BM Alliance Coal Operations Pty Limited QLD 1.36 Mt +469 kt ACCU buyer
Centurion Coal Mine Centurion Coal Mining Pty Ltd QLD 591 kt +430 kt ACCU + SMC
Warkworth Mine Warkworth Mining Ltd NSW 1.06 Mt +302 kt ACCU buyer
Olive Downs Complex PEMBROKE RESOURCES NOMINEE PTY LTD QLD 393 kt +293 kt ACCU buyer
← All Safeguard facilities
Source: Clean Energy Regulator — Safeguard Mechanism data · All figures in tCO₂-e · Data updated annually on CER release
All data sourced from the Clean Energy Regulator (Australian Government). Zerra is an independent data platform and is not affiliated with any listed facility or operator.