Rail
The Safeguard Mechanism requires Australia's largest industrial facilities to keep net emissions under a legislated, stepping-down baseline — or offset the difference with carbon credits.
Reported emissions vs baseline, 2018–19 to 2024–25
Credit surrenders — Rail
| Year | Emissions | Baseline | Gap† | ACCUs | SMCs | Compliance† |
|---|---|---|---|---|---|---|
| 24–25 | 265 kt | 241 kt | +24 kt | 10,314 | 13,513 | ACCU + SMC |
| 23–24 | 255 kt | 242 kt | +13 kt | 4,002 | 9,163 | ACCU + SMC |
| 22–23 | 259 kt | 312 kt | -53 kt | — | — | Under baseline |
| 21–22 | 245 kt | 311 kt | -65 kt | — | — | Under baseline |
| 20–21 | 285 kt | 280 kt | +5 kt | 11,776 | — | ACCU buyer |
| 18–19 | 192 kt | — | — | 1,470 | — | — |
Emissions, baseline, ACCUs and SMCs are reported directly by CER. †Gap and compliance category are calculated by Zerra from those figures.
What this means
Rail is a facility operated by THE PILBARA INFRASTRUCTURE PTY LTD in WA. Like all covered facilities, industrial operations generate significant emissions. Under Australia's Safeguard Mechanism, Rail must keep its annual emissions below a stepping-down baseline — or purchase carbon credits to cover any overage.
In 2024–25, Rail reported emissions of 265 kt against a baseline obligation of 241 kt — an overage of 24 kt. The facility covered the overage through a combination of ACCUs and SMCs.
Purchasing credits is legal and intended by the Safeguard Mechanism's design — the policy deliberately allows facilities to choose between cutting on-site emissions or funding abatement elsewhere in the economy. Whether credit purchases represent genuine long-term decarbonisation depends on whether the facility's absolute emissions are trending down over time. The chart above shows the trajectory since reporting began. This question applies to all covered facilities under the Safeguard Mechanism, not Rail specifically.
Among 5 comparable facilities, 5 reported emissions above their baseline in 2024–25. The table below compares Rail with other facilities covered by the Safeguard Mechanism in the same classification.
Related facilities — Safeguard Mechanism 2024–25
| Facility | Operator | State | Emissions | vs Baseline | Compliance |
|---|---|---|---|---|---|
| Pacific National National Transport Facility | PACIFIC NATIONAL PTY LTD | National | 728 kt | +85 kt | ACCU buyer |
| Aurizon National Transport Facility | AURIZON OPERATIONS LIMITED | National | 659 kt | +84 kt | ACCU buyer |
| Pilbara Rail Operations | PILBARA IRON PTY LTD | WA | 651 kt | +81 kt | ACCU buyer |
| PRL03 Rail - IOR Facility | BHP IRON ORE PTY LTD | WA | 552 kt | +48 kt | ACCU buyer |
| Rail | THE PILBARA INFRASTRUCTURE PTY LTD | WA | 265 kt | +24 kt | ACCU + SMC |
All data sourced from the Clean Energy Regulator (Australian Government). Zerra is an independent data platform and is not affiliated with any listed facility or operator.