North West Shelf Project
The Safeguard Mechanism requires Australia's largest industrial facilities to keep net emissions under a legislated, stepping-down baseline — or offset the difference with carbon credits.
Reported emissions vs baseline, 2016–17 to 2024–25
Credit surrenders — North West Shelf Project
| Year | Emissions | Baseline | Gap† | ACCUs | SMCs | Compliance† |
|---|---|---|---|---|---|---|
| 24–25 | 5.75 Mt | 4.83 Mt | +921 kt | 681,895 | 239,200 | ACCU + SMC |
| 23–24 | 6.10 Mt | 5.49 Mt | +608 kt | 607,982 | — | ACCU buyer |
| 22–23 | 6.94 Mt | — | — | 6,254 | — | — |
| 21–22 | 6.42 Mt | — | — | — | — | — |
| 20–21 | 6.78 Mt | — | — | — | — | — |
| 19–20 | 6.88 Mt | 7.57 Mt | -693 kt | — | — | Under baseline |
| 18–19 | 7.39 Mt | — | — | — | — | — |
| 17–18 | 7.65 Mt | — | — | — | — | — |
| 16–17 | 7.66 Mt | 22.71 Mt | -15.06 Mt | — | — | Under baseline |
Emissions, baseline, ACCUs and SMCs are reported directly by CER. †Gap and compliance category are calculated by Zerra from those figures.
What this means
North West Shelf Project is a facility operated by Woodside Energy Ltd. in WA. Like all covered facilities, industrial operations generate significant emissions. Under Australia's Safeguard Mechanism, North West Shelf Project must keep its annual emissions below a stepping-down baseline — or purchase carbon credits to cover any overage.
In 2024–25, North West Shelf Project reported emissions of 5.75 Mt against a baseline obligation of 4.83 Mt — an overage of 921 kt. The facility covered the overage through a combination of ACCUs and SMCs.
Purchasing credits is legal and intended by the Safeguard Mechanism's design — the policy deliberately allows facilities to choose between cutting on-site emissions or funding abatement elsewhere in the economy. Whether credit purchases represent genuine long-term decarbonisation depends on whether the facility's absolute emissions are trending down over time. The chart above shows the trajectory since reporting began. This question applies to all covered facilities under the Safeguard Mechanism, not North West Shelf Project specifically.
Among 8 comparable facilities, 8 reported emissions above their baseline in 2024–25. The table below compares North West Shelf Project with other facilities covered by the Safeguard Mechanism in the same classification.
Related facilities — Safeguard Mechanism 2024–25
| Facility | Operator | State | Emissions | vs Baseline | Compliance |
|---|---|---|---|---|---|
| North West Shelf Project | Woodside Energy Ltd. | WA | 5.75 Mt | +921 kt | ACCU + SMC |
| Gorgon Operations | CHEVRON AUSTRALIA PTY LTD | WA | 9.02 Mt | +478 kt | ACCU buyer |
| Gippsland Basin facility | ESSO AUSTRALIA RESOURCES PTY LTD | VIC | 1.63 Mt | +305 kt | ACCU buyer |
| Montara Operations | JADESTONE ENERGY (EAGLE) PTY LTD | NT | 284 kt | +163 kt | ACCU buyer |
| Queensland Curtis LNG Plant | QCLNG Operating Company Pty Ltd | QLD | 1.86 Mt | +158 kt | ACCU + SMC |
| APLNG Facility | CONOCOPHILLIPS AUSTRALIA OPERATIONS PTY LTD | QLD | 2.21 Mt | +147 kt | SMC buyer |
| Pluto LNG | Woodside Burrup Pty. Ltd. | WA | 1.89 Mt | +145 kt | ACCU buyer |
| Varanus Hub | Santos Limited | WA | 313 kt | +85 kt | ACCU + SMC |
All data sourced from the Clean Energy Regulator (Australian Government). Zerra is an independent data platform and is not affiliated with any listed facility or operator.