QLD · Safeguard Mechanism 2024–25

Curtis Island GLNG Plant

GLNG OPERATIONS PTY LTD
📍 QLD

The Safeguard Mechanism requires Australia's largest industrial facilities to keep net emissions under a legislated, stepping-down baseline — or offset the difference with carbon credits.

Curtis Island GLNG Plant reported emissions +66 kt above its baseline in 2024–25. The overage was covered using Safeguard Mechanism Credits (SMCs).
Source: Clean Energy Regulator · data as at 25 Oct 2026
1.68 Mt
2024–25 emissions CER
1.61 Mt
net baseline obligation CER
+66 kt
vs baseline Zerra calc.
66,427
SMCs surrendered CER

Reported emissions vs baseline, 2016–17 to 2024–25

Red bars indicate emissions above baseline — covered by carbon credit purchases
0t529kt1.1Mt1.6Mt2.1Mt16–1717–1818–1919–2020–2121–2222–2323–2424–25 Emissions Overage Baseline

Credit surrenders — Curtis Island GLNG Plant

YearEmissionsBaseline Gap†ACCUsSMCsCompliance†
24–25 1.68 Mt 1.61 Mt +66 kt — 66,427 SMC buyer
23–24 1.64 Mt 1.70 Mt -60 kt — — Under baseline
22–23 1.61 Mt 1.81 Mt -202 kt — — Under baseline
21–22 1.69 Mt 1.89 Mt -202 kt — — Under baseline
20–21 1.73 Mt 1.89 Mt -158 kt — — Under baseline
19–20 1.59 Mt 1.89 Mt -294 kt — — Under baseline
18–19 1.49 Mt 1.68 Mt -197 kt — — Under baseline
17–18 1.57 Mt 1.68 Mt -115 kt — — Under baseline
16–17 1.58 Mt 1.68 Mt -105 kt — — Under baseline

Emissions, baseline, ACCUs and SMCs are reported directly by CER. †Gap and compliance category are calculated by Zerra from those figures.

What this means

Curtis Island GLNG Plant is a facility operated by GLNG OPERATIONS PTY LTD in QLD. Like all covered facilities, industrial operations generate significant emissions. Under Australia's Safeguard Mechanism, Curtis Island GLNG Plant must keep its annual emissions below a stepping-down baseline — or purchase carbon credits to cover any overage.

In 2024–25, Curtis Island GLNG Plant reported emissions of 1.68 Mt against a baseline obligation of 1.61 Mt — an overage of 66 kt. The facility covered the overage using 66,427 Safeguard Mechanism Credits (SMCs) — credits generated by other covered facilities that came in under their own baselines.

Among 8 comparable facilities, 8 reported emissions above their baseline in 2024–25. The table below compares Curtis Island GLNG Plant with other facilities covered by the Safeguard Mechanism in the same classification.

Related facilities — Safeguard Mechanism 2024–25

Facility Operator State Emissions vs Baseline Compliance
North West Shelf Project Woodside Energy Ltd. WA 5.75 Mt +921 kt ACCU + SMC
Gorgon Operations CHEVRON AUSTRALIA PTY LTD WA 9.02 Mt +478 kt ACCU buyer
Gippsland Basin facility ESSO AUSTRALIA RESOURCES PTY LTD VIC 1.63 Mt +305 kt ACCU buyer
Montara Operations JADESTONE ENERGY (EAGLE) PTY LTD NT 284 kt +163 kt ACCU buyer
Queensland Curtis LNG Plant QCLNG Operating Company Pty Ltd QLD 1.86 Mt +158 kt ACCU + SMC
APLNG Facility CONOCOPHILLIPS AUSTRALIA OPERATIONS PTY LTD QLD 2.21 Mt +147 kt SMC buyer
Pluto LNG Woodside Burrup Pty. Ltd. WA 1.89 Mt +145 kt ACCU buyer
Varanus Hub Santos Limited WA 313 kt +85 kt ACCU + SMC
← All Safeguard facilities
Source: Clean Energy Regulator — Safeguard Mechanism data · All figures in tCO₂-e · Data updated annually on CER release
All data sourced from the Clean Energy Regulator (Australian Government). Zerra is an independent data platform and is not affiliated with any listed facility or operator.