Updates

Follow the data.

New data and updates — no noise. We'll let you know when something worth knowing happens.

Electricity Generation · WA · Safeguard Mechanism 2023–24

Solomon Power Station

FMG SOLOMON PTY LTD
📍 WAElectricity GenerationABN 95 128 959 179Baseline: Production-adjusted baseline
Solomon Power Station came in under its baseline in 2023–24 — reporting 317 kt against an obligation of 367 kt.
317 kt
2023–24 emissions
367 kt
net baseline obligation
-50 kt
vs baseline
ACCUs surrendered
Emissions history

Reported emissions vs baseline, 2024–2024

Red bars indicate emissions above baseline — covered by carbon credit purchases
0t103kt205kt308kt411kt24–25 Emissions Overage Baseline
Annual compliance record

Credit surrenders — Solomon Power Station

YearEmissionsBaseline GapACCUsSMCsCompliance
24–25 317 kt 367 kt -50 kt Under baseline
Plain English

What this means

Solomon Power Station is a electricity generation facility operated by FMG SOLOMON PTY LTD in WA. Like all covered facilities, industrial operations generate significant emissions. Under Australia's Safeguard Mechanism, Solomon Power Station must keep its annual emissions below a stepping-down baseline — or purchase carbon credits to cover any overage.

In 2023–24, Solomon Power Station came in under its baseline — reporting emissions of 317 kt against an obligation of 367 kt, a surplus of 50 kt. Facilities that come in under baseline can generate Safeguard Mechanism Credits (SMCs), which can be sold to facilities that need to cover an overage. Solomon Power Station generated 49,749 SMCs in 2023–24.

Across the electricity generation sector, 3 of 6 covered facilities reported emissions above their baseline in 2023–24. The table below compares Solomon Power Station with other electricity generation facilities covered by the Safeguard Mechanism.

Other facilities — Electricity Generation

Electricity Generation facilities — Safeguard Mechanism 2023–24

Facility Operator State Emissions vs Baseline Compliance
Yarnima Power Station BHP IRON ORE PTY LTD WA 348 kt +19 kt ACCU buyer
McArthur River Power Station EDL NGD (NT) Pty Ltd NT 153 kt +15 kt ACCU buyer
Leinster Power Station TEC DESERT PTY LTD WA 133 kt +4 kt ACCU buyer
Mt Keith Power Station TEC DESERT PTY LTD WA 160 kt -597 t Under baseline
Solomon Power Station FMG SOLOMON PTY LTD WA 317 kt -50 kt Under baseline
Newman Power Station APA TRANSMISSION (ROY HILL) PTY LTD WA 376 kt -115 kt Under baseline
← All Safeguard facilities
Source: Clean Energy Regulator — Safeguard Mechanism published data 2023–24 · All figures in tCO₂-e · Methodology · Data updated annually on CER release
All data sourced from the Clean Energy Regulator (Australian Government). Zerra is an independent data platform and is not affiliated with any listed facility or operator.