WA · Safeguard Mechanism 2024–25

Fimiston Operations

KALGOORLIE CONSOLIDATED GOLD MINES PTY LTD
📍 WA

The Safeguard Mechanism requires Australia's largest industrial facilities to keep net emissions under a legislated, stepping-down baseline — or offset the difference with carbon credits.

Fimiston Operations reported emissions +146 kt above its baseline in 2024–25. The overage was covered through a mix of ACCUs and SMCs.
Source: Clean Energy Regulator · data as at 25 Oct 2026
271 kt
2024–25 emissions CER
125 kt
net baseline obligation CER
+146 kt
vs baseline Zerra calc.
136,139
ACCUs surrendered CER

Reported emissions vs baseline, 2021–22 to 2024–25

Red bars indicate emissions above baseline — covered by carbon credit purchases
0t76kt152kt228kt304kt21–2222–2323–2424–25 Emissions Overage Baseline

Credit surrenders — Fimiston Operations

YearEmissionsBaseline Gap†ACCUsSMCsCompliance†
24–25 271 kt 125 kt +146 kt 136,139 9,746 ACCU + SMC
23–24 230 kt 137 kt +93 kt 92,932 — ACCU buyer
22–23 229 kt 243 kt -14 kt — — Under baseline
21–22 192 kt 243 kt -50 kt — — Under baseline

Emissions, baseline, ACCUs and SMCs are reported directly by CER. †Gap and compliance category are calculated by Zerra from those figures.

What this means

Fimiston Operations is a facility operated by KALGOORLIE CONSOLIDATED GOLD MINES PTY LTD in WA. Like all covered facilities, industrial operations generate significant emissions. Under Australia's Safeguard Mechanism, Fimiston Operations must keep its annual emissions below a stepping-down baseline — or purchase carbon credits to cover any overage.

In 2024–25, Fimiston Operations reported emissions of 271 kt against a baseline obligation of 125 kt — an overage of 146 kt. The facility covered the overage through a combination of ACCUs and SMCs.

Purchasing credits is legal and intended by the Safeguard Mechanism's design — the policy deliberately allows facilities to choose between cutting on-site emissions or funding abatement elsewhere in the economy. Whether credit purchases represent genuine long-term decarbonisation depends on whether the facility's absolute emissions are trending down over time. The chart above shows the trajectory since reporting began. This question applies to all covered facilities under the Safeguard Mechanism, not Fimiston Operations specifically.

Among 8 comparable facilities, 8 reported emissions above their baseline in 2024–25. The table below compares Fimiston Operations with other facilities covered by the Safeguard Mechanism in the same classification.

Related facilities — Safeguard Mechanism 2024–25

Facility Operator State Emissions vs Baseline Compliance
Brockman 2 / Nammuldi Mines Hamersley Iron Pty. Limited WA 305 kt +153 kt ACCU buyer
Fimiston Operations KALGOORLIE CONSOLIDATED GOLD MINES PTY LTD WA 271 kt +146 kt ACCU + SMC
Solomon Mine FMG SOLOMON PTY LTD WA 471 kt +113 kt ACCU + SMC
Roy Hill Mine Roy Hill Holdings Pty Ltd WA 481 kt +87 kt ACCU buyer
Cloudbreak Mine CHICHESTER METALS PTY LTD WA 332 kt +85 kt ACCU + SMC
Gruyere Mine Site Gruyere Mining Company Pty Ltd WA 268 kt +77 kt ACCU buyer
Brockman 4 Mine Hamersley Iron Pty. Limited WA 233 kt +68 kt ACCU buyer
Newman Operations BHP IRON ORE PTY LTD WA 347 kt +65 kt ACCU buyer
← All Safeguard facilities
Source: Clean Energy Regulator — Safeguard Mechanism data · All figures in tCO₂-e · Data updated annually on CER release
All data sourced from the Clean Energy Regulator (Australian Government). Zerra is an independent data platform and is not affiliated with any listed facility or operator.