NKW01 Nickel West Kwinana Facility
The Safeguard Mechanism requires Australia's largest industrial facilities to keep net emissions under a legislated, stepping-down baseline — or offset the difference with carbon credits.
Reported emissions vs baseline, 2016–17 to 2024–25
Credit surrenders — NKW01 Nickel West Kwinana Facility
| Year | Emissions | Baseline | Gap† | ACCUs | SMCs | Compliance† |
|---|---|---|---|---|---|---|
| 24–25 | 60 kt | 100 kt | -40 kt | — | — | Under baseline |
| 23–24 | 169 kt | 122 kt | +47 kt | 62,720 | 17,666 | ACCU + SMC |
| 22–23 | 166 kt | — | — | — | — | — |
| 21–22 | 162 kt | — | — | — | — | — |
| 20–21 | 171 kt | 176 kt | -6 kt | — | — | Under baseline |
| 19–20 | 157 kt | 181 kt | -25 kt | — | — | Under baseline |
| 18–19 | 164 kt | 181 kt | -17 kt | — | — | Under baseline |
| 17–18 | 162 kt | 181 kt | -20 kt | — | — | Under baseline |
| 16–17 | 163 kt | 181 kt | -19 kt | — | — | Under baseline |
Emissions, baseline, ACCUs and SMCs are reported directly by CER. †Gap and compliance category are calculated by Zerra from those figures.
What this means
NKW01 Nickel West Kwinana Facility is a facility operated by BHP NICKEL WEST PTY LTD in WA. Like all covered facilities, industrial operations generate significant emissions. Under Australia's Safeguard Mechanism, NKW01 Nickel West Kwinana Facility must keep its annual emissions below a stepping-down baseline — or purchase carbon credits to cover any overage.
In 2024–25, NKW01 Nickel West Kwinana Facility came in under its baseline — reporting emissions of 60 kt against an obligation of 100 kt, a surplus of 40 kt. Facilities that come in under baseline can generate Safeguard Mechanism Credits (SMCs), which can be sold to facilities that need to cover an overage.
Among 8 comparable facilities, 8 reported emissions above their baseline in 2024–25. The table below compares NKW01 Nickel West Kwinana Facility with other facilities covered by the Safeguard Mechanism in the same classification.
Related facilities — Safeguard Mechanism 2024–25
| Facility | Operator | State | Emissions | vs Baseline | Compliance |
|---|---|---|---|---|---|
| Queensland Alumina Limited Refinery | QUEENSLAND ALUMINA LIMITED | QLD | 3.17 Mt | +356 kt | ACCU buyer |
| Rio Tinto Yarwun | RTA Yarwun Pty Ltd | QLD | 2.05 Mt | +135 kt | ACCU buyer |
| WOR01 | South32 Worsley Alumina Pty Ltd | WA | 3.22 Mt | +132 kt | ACCU + SMC |
| Wagerup Alumina Refinery | Alcoa of Australia Limited | WA | 1.31 Mt | +90 kt | SMC buyer |
| Tomago Aluminium Smelter | TOMAGO ALUMINIUM COMPANY PTY LTD | NSW | 1.09 Mt | +56 kt | ACCU buyer |
| Kwinana Alumina Refinery | Alcoa of Australia Limited | WA | 140 kt | +40 kt | SMC buyer |
| Portland Aluminium Smelter | Alcoa Portland Aluminium Proprietary Limited | VIC | 600 kt | +36 kt | ACCU + SMC |
| Gove Operations | RTA GOVE PTY LIMITED | NT | 136 kt | +27 kt | ACCU buyer |
All data sourced from the Clean Energy Regulator (Australian Government). Zerra is an independent data platform and is not affiliated with any listed facility or operator.