Boyne Smelters Limited
The Safeguard Mechanism requires Australia's largest industrial facilities to keep net emissions under a legislated, stepping-down baseline — or offset the difference with carbon credits.
Reported emissions vs baseline, 2016–17 to 2024–25
Credit surrenders — Boyne Smelters Limited
| Year | Emissions | Baseline | Gap† | ACCUs | SMCs | Compliance† |
|---|---|---|---|---|---|---|
| 24–25 | 944 kt | 921 kt | +23 kt | 13,160 | 9,745 | ACCU + SMC |
| 23–24 | 922 kt | 931 kt | -10 kt | — | — | Under baseline |
| 22–23 | 909 kt | 859 kt | +50 kt | 49,701 | — | ACCU buyer |
| 21–22 | 896 kt | 919 kt | -23 kt | — | — | Under baseline |
| 20–21 | 899 kt | 919 kt | -20 kt | — | — | Under baseline |
| 19–20 | 905 kt | 919 kt | -14 kt | — | — | Under baseline |
| 18–19 | 954 kt | 1.05 Mt | -99 kt | — | — | Under baseline |
| 17–18 | 933 kt | 1.05 Mt | -120 kt | — | — | Under baseline |
| 16–17 | 997 kt | 1.05 Mt | -56 kt | — | — | Under baseline |
Emissions, baseline, ACCUs and SMCs are reported directly by CER. †Gap and compliance category are calculated by Zerra from those figures.
What this means
Boyne Smelters Limited is a facility operated by RIO TINTO ALUMINIUM LIMITED in QLD. Like all covered facilities, industrial operations generate significant emissions. Under Australia's Safeguard Mechanism, Boyne Smelters Limited must keep its annual emissions below a stepping-down baseline — or purchase carbon credits to cover any overage.
In 2024–25, Boyne Smelters Limited reported emissions of 944 kt against a baseline obligation of 921 kt — an overage of 23 kt. The facility covered the overage through a combination of ACCUs and SMCs.
Purchasing credits is legal and intended by the Safeguard Mechanism's design — the policy deliberately allows facilities to choose between cutting on-site emissions or funding abatement elsewhere in the economy. Whether credit purchases represent genuine long-term decarbonisation depends on whether the facility's absolute emissions are trending down over time. The chart above shows the trajectory since reporting began. This question applies to all covered facilities under the Safeguard Mechanism, not Boyne Smelters Limited specifically.
Among 8 comparable facilities, 8 reported emissions above their baseline in 2024–25. The table below compares Boyne Smelters Limited with other facilities covered by the Safeguard Mechanism in the same classification.
Related facilities — Safeguard Mechanism 2024–25
| Facility | Operator | State | Emissions | vs Baseline | Compliance |
|---|---|---|---|---|---|
| Queensland Alumina Limited Refinery | QUEENSLAND ALUMINA LIMITED | QLD | 3.17 Mt | +356 kt | ACCU buyer |
| Rio Tinto Yarwun | RTA Yarwun Pty Ltd | QLD | 2.05 Mt | +135 kt | ACCU buyer |
| WOR01 | South32 Worsley Alumina Pty Ltd | WA | 3.22 Mt | +132 kt | ACCU + SMC |
| Wagerup Alumina Refinery | Alcoa of Australia Limited | WA | 1.31 Mt | +90 kt | SMC buyer |
| Tomago Aluminium Smelter | TOMAGO ALUMINIUM COMPANY PTY LTD | NSW | 1.09 Mt | +56 kt | ACCU buyer |
| Kwinana Alumina Refinery | Alcoa of Australia Limited | WA | 140 kt | +40 kt | SMC buyer |
| Portland Aluminium Smelter | Alcoa Portland Aluminium Proprietary Limited | VIC | 600 kt | +36 kt | ACCU + SMC |
| Gove Operations | RTA GOVE PTY LIMITED | NT | 136 kt | +27 kt | ACCU buyer |
All data sourced from the Clean Energy Regulator (Australian Government). Zerra is an independent data platform and is not affiliated with any listed facility or operator.